Livin
22/10/2011
The livin staff have moved in.
28/09/2011
Work on the car park and surrounding area is now complete.
16/09/2011
The final touches have been made to the external brickwork in the South and East elevations.
10/09/2011
This month has seen the installation of the external Louver system.
28/08/2011
All hands are on deck at the Livin offices.
18/07/2011
Raised access flooring has been installed.
03/07/2011
Summer has arrived at Livin!
10/06/2011
Local construction company P. James has started external brick work.
25/05/2011
The newly built road will be pivotal in providing easy access to Livin's headquarters.
16/05/2011
The team have successfully completed the thermal installation board to the external of the building.
28/04/2011
Work has moved from outside the Livin Building and the DurhamGate team have successfully started work.
26/04/2011
The team on site have today started work on the installation of the curtain wall around the internal elevations of the Livin Building.
15/04/2011
As we progress further and further on site, our work force have begun digging up the perimeter of the Livin Building.
05/04/2011
Hoping that all the winter weather is behind us, the sunshine and overall progress has brought extra motivation to the DurhamGate site
16/03/2011
February was a busy month for Carillion and the contractors on site.
28/02/2011
February was a busy month for Carillion and the contractors on site.
21/02/2011
February has been a month that has seen significant progression and the hard work has resulted in a commanding physical presence on the site.
31/01/2011
Rainton Groundworks has begun digging strip and pad foundations to enable the steel frames to be built on.
31/12/2010
Our fantastic workforce powers through the unforgiving weather conditions